PROJECT UPDATE – CORMACK DRIVE & PRINCE STREET

June 19, 2019

PROJECT UPDATE – June 17, 2019

WATER & SEWER UPGRADES – CORMACK DRIVE PHASE II & III & PRINCE STREET

Click Here to Download Notice & Location Map

As residents are aware, construction on Cormack Drive is into the third week. Thus far the project is progressing well with minor inconveniences which we apologize for.

We would like to inform you that with the contractor’s introduction of a second crew, construction on Prince Street will be starting this week. Previously the contractor planned to finish Cormack Drive but feel that working simultaneously on Cormack and Prince Street will prove to be beneficial to all.

Once again, thank you for your cooperation and understanding and apologize for any convenience.

Some residents may be under a boil water advisory as construction progresses and temporary water lines are installed.

RESIDENTS WILL BE NOTIFIED DIRECTLY IF YOU ARE AFFECTED BY ANY TEMPORARY BOIL WATER ADVISORY. If you haven’t been contacted directly, you are not under a boil water advisory.

Who Can You Call?


Working Hours
Our contractor’s normal working hours are from 7 a.m. to 7 p.m. Monday to Thursday and 7 a.m. to noon on Friday. We apologize for any inconvenience this may cause.

Thank you!
Rick Wells, Director of External Operations